Bio-SMART & INCOM Project Meeting
September 18, 2013, 9:00 – 17:00, KWR Offices
Proposed Agenda
8:30 Coffee | |
9:00 Welcome | Prof. Gertjan Medema (KWR) |
9:15 Introduction – Meeting objectives | Prof. Ilan Juran (W-SMART) |
1. WP1 – Interactive Framework for End-Users’ Priority Objectives & Technical Requirements
This task requires an interactive framework based upon use case analysis, identifying performance matrix and datasets provided by the utilities. In the last project Meeting, May 13, the current State-of-Practice consisting of non-specific on-line monitoring for early bio-anomaly detection was presented by the utilities with data analysis examples in order to create a concrete framework for identifying the operator processes, datasets and requirements for the Bio-SMART system adaptation/prototyping, including:
- VIGIRESEAU recommended approach presented by Dr. Daniel Villessot (LDE),
- EDP Active Chlorine Monitoring presented by Bruno Nguyen (EDP)
- VIP Multi-parameter (TOC; Conductivity; Optica sensors; other) Monitoring presented by Dr. Bendert de Graaf (VITENS)
The operators have agreed to provide the Research Teams access to relevant datasets with data analysis examples of use cases for assessment of the data attributes, basic pre-processing and early configuration of current processes, early detection systems and data quality control procedures. Current effort focused primarily on early configuration of EDP leak detection process as SWN application – EDP, CEA LIST, CALM WATER, W-SMART. Discussion agenda includes:
9:30 System Technical Requirements & Performance matrix |
Bruno Nguyen (EDP) |
9:45 INCOM System Requirements | Frank Montiel (EDP) |
10:00 Use Case Analysis – Leak Detection | John Johnson (CW), Dr. Cedric Auliac (CEA LIST) |
10:30 Bio-SMART System Requirements & Data Quality Control | Prof. Gertjan Medema (KWR), Dr. Laurent Moulin (EDP), Dr. Bendert de Graaf (VITENS) |
11:00 Discussion – Bio-SMART Requirements & Use Case Analysis | Prof. Gertjan Medem |
System Requirements, Data Quality Control, Identification of relevant datasets provided by the utilities, assessment of the data attributes, basic pre-processing and early configuration of current detection processes | |
11:45 Next Step | John Johnson (CW) & Dr. Cedric Auliac (CEA LIST) |
2. WPII – USTL Site Characterization & Instrumentation/Monitoring Planning
13:00 USTL Site Characterization & Instrumentation Planning | Prof. Isam Shahrour (USTL, LGCgE) & Jean-Marc Charlemagne (SEN) |
13:30 Comments based upon VIP Site Experience | Dr. Bendert de Graaf (VITENS) |
|
|
14:45 Next Step – Site Instrumentation & Monitoring Planning | Jean-Marc Charlemagne (SEN) |
13:45 Proposed discussion issues: | Prof. Gertjan Medema (KWR) |
3. Project Management Issues for both INCOM & BIO-SMART projects
15:00 Review updated WP scoping and timetable | Prof. Gertjan Medema (KWR) |
15:30 Project Management, IP Protection, Invoicing | Prof. Ilan Juran (W-SMART) |
16:00 SMARTWATER4EU | Dr. Bendert de Graaf (VITENS) |
16:30 INCOM Project Update (MOU with KWR) | Prof. Ilan Juran (W-SMART) |
17:00 Conclusion | Bruno Nguyen (EDP) |